Skip to content
CONFIGLANE

Procurement · Operations

Meraki licensing: Co-Term vs Subscription — which model fits?

Choosing a Meraki licence starts with the organisation's licensing model, not the hardware quote. This guide compares Co-Term and Subscription, shows what adding devices does to renewal planning, and explains what to check before expiry or a model change.

By ConfiglanePublished Updated 13 min readCisco Meraki

The short version

  • Meraki runs three licensing models: subscription, co-termination and per-device. Per-device no longer takes on customers moving to it where subscription licensing is available, so in practice the choice is between the first two.
  • Co-termination averages all active licences onto one shared expiration date. The calculation follows the licence limit, not the current device count: removing hardware does not push the date out.
  • Subscription operates at network level rather than organisation-wide, allowing different tiers within one organisation. Terms run from 36 to 84 months with customer-determined start and end dates.
  • At expiry the models part ways: under co-termination and per-device the hardware becomes non-operational. Under subscription traffic keeps flowing and manageability is withdrawn instead — on a last-in, first-out basis.

Plan additional licences: Use the co-term calculator to simulate the new term. Procurement also depends on which licensing model carries the organisation: it determines when you renew, which networks share a deadline, and what happens after expiry and the grace period. And it cannot be swapped at will.

Three models, two of them still a choice

Meraki documents three licensing models: subscription, co-termination and per-device licensing (PDL). The third is effectively closed — it is no longer available to customers who would like to move to it in regions where subscription licensing is available. Existing PDL organisations carry on, but a fresh decision comes down to subscription or co-termination.

Co-terminationSubscription
Scopethe whole organisationnetworks bind to a subscription; several networks can share it
Expiryone shared, averaged dateper subscription, start and end chosen by you
Terms1, 3, 5, 7 and 10 years36 to 84 months
Billingprepaidmonthly, quarterly, annual or prepaid
At expiryhardware becomes non-operationaltraffic continues, management stops
Availabilityglobalglobal except Russia and Belarus; check regional cloud requirements
The two models side by side

Co-termination: one date for everything

Co-termination brings every licence in an organisation onto the same expiration date. Meraki describes the arithmetic openly: all active licences are averaged together and divided by the licence limit count of devices in the organisation. The result is the remaining term — for every device at once.

For a branch estate that grows over years, that is the decisive property: additional licences for a new site can change the shared date. This is not a flaw but the purpose of the model — one deadline, one renewal, one invoice. It also means the renewal date of a growing organisation keeps moving and cannot simply be pinned to a fixed month.

Co-term licence calculator: simulate the shared date

Meraki's own licence calculator sits in the dashboard behind the login — useful in operation, out of reach at quoting time. For the order of magnitude before a purchase, the documented arithmetic is enough, and that is exactly what this calculator implements: existing positions with their remaining days, new licences with their full term.

Interactive

Rows work like the dashboard: devices and remaining licence days per existing position, new licences with their full term. The price weight mirrors Meraki's dollar-days weighting — while all devices share one price class, leave it at 1.

DevicesLicence daysPrice weight

Shared remaining term

851days

Method as Meraki documents it: the sum of weight × devices × days, divided by the weighted device count, rounded to whole days. The licence calculator in the dashboard is authoritative — the sources at the end of the article carry both procedures.

Subscription: term per network, not per organisation

Subscription moves licensing from the organisation down to the network level. A network binds to exactly one subscription at a time; several networks in the same organisation can share a subscription. A separate site therefore does not automatically have a separate contract deadline. Different MX tiers are possible within one organisation under different subscriptions.

  • Terms of 36 to 84 months, with start and end dates you determine — the deadline follows your contract year, not the accident of the order in which keys were claimed.
  • Billing monthly, quarterly, annually or prepaid rather than prepaid only.
  • Feature tiers can be upgraded without rebuilding the licence structure.
  • Available globally except in Russia and Belarus. Cisco lists local purchasing for India and Canada, but claiming and management currently use meraki.com, not meraki.in or meraki.ca.

Essentials vs Advantage: the tier question

Within subscription licensing the second decision follows: the feature tier — Essentials or Advantage, chosen per network and product class (wireless, switching, security/SD-WAN). The vocabulary belongs to subscription; under co-termination the MX editions are instead called Enterprise, Advanced Security and Secure SD-WAN Plus. A quote that mixes the two naming worlds compares apples with pears.

The MX shows what the tier separates: Advantage bundles, among other things, the ThousandEyes integration including internet outage analysis, Adaptive Policy (SGT assignment), SD-Internet steering, and web app, WAN and VoIP health — Essentials carries the core feature set. One exception is documented explicitly: the vMX does not support the Advantage tier; a network with a claimed vMX cannot set it for that product class.

  • Tier per network and product class — headquarters can run Advantage while a branch gets by on Essentials, in the same organisation.
  • Upgrade without rebuild: moving from Essentials to Advantage is a documented upgrade path, not a new licensing project.
  • A 30-day Advantage trial per network and product class, free of charge. Afterwards the class automatically drops back to Essentials — traffic and basic management continue, only the Advantage features end. The same class can be retried after 45 days.

What happens at expiry — where the similarity ends

Both models grant a 30-day grace period on non-compliance. After that they behave fundamentally differently, and that difference is the real reason to choose the model deliberately.

Under co-termination and PDL the affected hardware becomes non-operational: it can no longer be configured, and the network products no longer allow traffic to pass to the internet. A missed date is an outage.

Under subscription the network keeps running. Organisations that are both out of compliance and past the 30-day grace period continue to function and forward data traffic — Meraki sets this explicitly against the previous model's shutdown procedure. Automated enforcement instead withdraws manageability from the non-compliant devices, on a last-in, first-out basis.

Plan licence renewal and hardware lifecycle together

Licence expiry, end-of-sale (EOS) and end-of-support (EOST) are separate dates. EOS is the last ordering date for a product; EOST ends its affirmative vendor support. An installed device reaching EOS does not simultaneously lose its licence or automatically shut down. Renewing a licence likewise does not extend EOST. Use the specific product notice for the hardware plan, rather than an assumed service life.

  1. Keep a planning record with a named owner

    Record organisation, networks, licensing model, subscription binding, product class and tier, hardware types and quantities, expiry, the EOS/EOST source, replacement date and owners. This is your planning register; it does not assume an automatic combined lifecycle report in Dashboard.

  2. Set quantities and replacement scope before quoting

    For co-termination, reconcile deployed counts with licence limits by device type. A key claimed as a renewal replaces the earlier limits; missing items can leave the organisation out of compliance. For subscription, work from the networks actually bound to it and their required quantities.

  3. Give each lead time an outcome

    As an internal planning rule, review inventory and hardware plans 120 days ahead, settle the quote and budget 90 days ahead, and complete renewal 30 days ahead. These are suggested working intervals, not Cisco deadlines. Procurement and migration may need longer.

  4. Keep evidence of completion

    After renewal, reconcile the actual term, quantities and bindings with the order. Record the confirmed values and review date, then schedule the next deadline. Hardware replacement has its own work order and acceptance checks.

Filled example: three sites, two subscriptions

Network / estateSubscription / tier / licence endHardware assumption / replacementNext action / owner
Headquarters · 12 generation A APsSUB-A · Essentials · 31 March 2027Past EOS; fictional EOST 31 December 2028 · replace Q3 2028Plan renewal and replacement costs together by 1 December 2026 · IT lead
North branch · 6 generation A APsSUB-A · Essentials · 31 March 2027Same as headquarters · replace in the same Q3 2028 projectInclude 6 APs in the shared SUB-A quote · procurement
South branch · 4 generation B APsSUB-B · Essentials · 30 September 2029No EOST announced in this example · review lifecycle before the next hardware purchaseTrack its own subscription term; check quantities during expansion · site IT
Plan reviewed 7 September 2026 · Example Retail organisation · Wireless

The resulting decision: SUB-A covers 18 APs across two networks, SUB-B another four. The proposed SUB-A renewal through 31 March 2030 needs a plan to replace generation A before the end of 2028; a valid licence would not establish hardware support through the contract end. Under co-termination the calculation would differ: all licences in this organisation would share one date. New licence positions for expansion can be modelled in the calculator; an order still depends on the actual licence data.

What follows for procurement

  1. Decide the model before the hardware

    Because subscription keys cannot be claimed in an active legacy organisation, and the move from PDL to subscription is permanent, this is not a question for later.

  2. Model the growth, not the current state

    Under co-termination additional licence positions affect the shared date. If you will have twice the sites in three years, you should know where the deadline lands then.

  3. Put the expiry behaviour in writing

    Whether traffic stops or management stops at expiry belongs in the quote and in the operations manual — not in one person's memory.

  4. Plan lead time, not grace

    The 30 days are a safety net, not a process. A renewal that only starts when the warning appears was scheduled too late.

How we run licence terms in day-to-day operations — consolidated dates, planned renewals, lead time before every deadline — is described under Cisco Meraki. The structure that comes with it once many sites are involved — templates, claiming and the order of work — is covered in the piece on the Meraki multi-site rollout.

Sources

Every evidenced claim in this article can be traced here. The retrieval date shows how fresh the check is.

  1. Subscription — Licensing Network Bindingopens in a new tab

    Cisco Meraki Documentation · retrieved 7 September 2026

  2. Licensing — overview of the three modelsopens in a new tab

    Cisco Meraki Documentation · retrieved 26 August 2026

  3. Meraki Co-Termination Licensing Overviewopens in a new tab

    Cisco Meraki Documentation · retrieved 7 September 2026

  4. Subscription Licensingopens in a new tab

    Cisco Meraki Documentation · retrieved 7 September 2026

  5. Subscription — License Compliance Cloud Experienceopens in a new tab

    Cisco Meraki Documentation · retrieved 26 August 2026

  6. General Licensing FAQsopens in a new tab

    Cisco Meraki Documentation · retrieved 26 August 2026

  7. Subscription — MX Licensing (Essentials/Advantage tiers)opens in a new tab

    Cisco Meraki Documentation · retrieved 1 September 2026

  8. Subscription Advantage Feature Tier Trialsopens in a new tab

    Cisco Meraki Documentation · retrieved 1 September 2026

  9. The Science behind Licensing Co-Terminationopens in a new tab

    Cisco Meraki Documentation · retrieved 1 September 2026

  10. Using the License Calculatoropens in a new tab

    Cisco Meraki Documentation · retrieved 1 September 2026

  11. Meraki End-of-Life (EOL) Products and Datesopens in a new tab

    Cisco Meraki Documentation · retrieved 7 September 2026

FAQ

Frequently asked questions about Meraki licensing

Can we switch from co-termination to subscription?

Not casually. Subscription licence keys cannot be claimed in an organisation that is actively using a legacy model. For moving a PDL organisation to subscription, Meraki points to a support case and describes the conversion as permanent. In practice that makes the switch a project with lead time, not a toggle in the dashboard.

Does our expiry date move out if we decommission devices?

No. The shared co-termination date follows the organisation's licence limit, not the current device count. Removing hardware therefore does not push the deadline back. If you are permanently shrinking the estate, the limit itself has to be adjusted for that to show up in the calculation.

What happens if we add a site mid-year?

Under co-termination the new licence enters the shared average and moves the expiration date of every existing device with it. The offset is accounted for: a licence claimed part-way through another's term enters the calculation with its remaining time, not its full term. Under subscription, binding decides: the network can share an existing subscription or use a separate subscription with its own term.

Does our network stop when a licence expires?

That depends on the model. Under co-termination and per-device the affected hardware becomes non-operational after the 30-day grace period and no longer lets traffic pass to the internet. Under subscription data traffic keeps flowing; what is withdrawn is manageability of the non-compliant devices, on a last-in, first-out basis. A network you can no longer configure is not a state you want to stay in either.

Which model suits a growing branch estate?

Subscription can suit sites that need separate contract cycles. That requires the appropriate subscription binding: several networks can also share a contract. Co-termination plays to its strength where the estate is stable and administrative effort matters: one date, one renewal, one invoice. The decision should follow planned growth, not the current headcount of devices.

What separates Essentials from Advantage?

The feature tier within subscription licensing, chosen per network and product class. On the MX, Advantage adds the ThousandEyes integration, Adaptive Policy and SD-Internet steering among others; the vMX does not support Advantage. Moving up from Essentials is a documented upgrade path, and each product class can run a free 30-day trial that automatically falls back to Essentials.

Is per-device licensing (PDL) still available?

For existing organisations, yes — they continue unchanged. In practice nobody new gets in: in regions where subscription licensing is available, PDL no longer accepts customers moving to it, and Meraki describes converting a PDL organisation to subscription as permanent. A fresh choice today is between subscription and co-termination.

How long is the Meraki licence grace period?

30 days, in both models. Under co-termination and per-device the affected hardware becomes non-operational afterwards; under subscription traffic keeps flowing and what is withdrawn is manageability of the non-compliant devices. The period is a safety net, not a process — a renewal that only starts when the warning appears was scheduled too late.

What do end-of-sale and end-of-support have to do with the licence?

They are two separate clocks. The licence ends with its term; hardware has separate sale and support milestones: end-of-sale is normally announced six months before the last order date, and end-of-support typically falls five years after end-of-sale. For planning that means a long licence term is no substitute for a hardware plan. Bringing in replacement devices with new licences shifts the shared expiry date of everyone else under co-termination — the calculator above shows by how much.

Cisco Meraki

Cisco Meraki operations. With clear ownership.

You have the dashboard. What you lack is time to operate it. We take on agreed operational responsibilities for your Meraki network, or work alongside your internal IT team in a co-managed model.

Discuss Meraki operations

Assessment → first dependable change